Hobart Stadium and Precinct Estimate Hits $1.545 Billion as Borrowing Looms
Tasmania's government has put the estimated cost of Hobart's Macquarie Point stadium and associated precinct works at $1.545 billion, with borrowing set to cover any funding shortfall.
The figures released on 24 November 2026 increase the financial pressure surrounding the project, while final procurement negotiations could still change the bill.
Stadium estimate is only part of the total
The Tasmanian Government's statement puts the stadium estimate at $1.23 billion. A further $132 million covers broader precinct infrastructure, including a centralised car park and power upgrades, while project delivery costs account for $183 million.
In the statement, republished by Mirage News, the government attributed the increase to construction-market pressures, higher oil and materials prices, labour costs and the project's complexity.
ABC News reported that an undisclosed client contingency is not included in the announced figures. The estimate should therefore not be read as a guaranteed final price.
State faces a larger borrowing task
The government says it is seeking additional contributions from project partners and will fund any shortfall through borrowing. It plans to market commercial opportunities across the precinct during 2027 to help recoup those borrowings.
ABC News reported that the state would exceed its previously promised $875 million contribution cap. Independent economist Saul Eslake told the broadcaster that the additional debt would carry a substantial interest cost.
Premier Jeremy Rockliff defended the project as an investment in jobs and economic opportunities. He also said the revised cost would not be returned to parliament for another approval.
Contract negotiations remain unfinished
The 23,000-seat roofed venue is a condition of Tasmania's AFL agreement, but the immediate issue is the cost to public finances rather than a change to the team's football operations.
Macquarie Point Development Corporation is negotiating with preferred tenderer BESIX Watpac. The government's statement makes clear that the final procurement phase is continuing and further cost changes remain possible.